How long it takes to build a website, from brief to launch.

Website timelines depend on the type of site, the features it needs and how ready your content is. Here are typical UK timelines, what happens in each phase and what most often causes delays.

How long does it take to build a website?

As a typical guide, a template-based starter site takes 1–3 weeks, a small business or custom WordPress site 4–8 weeks, an ecommerce site 6–12 weeks, a bespoke corporate site 2–4 months and a web application 3–6 months or more. Content readiness and feedback speed affect timelines as much as development.

How long do different types of website take?

Timelines scale with complexity. Simple sites using an existing template can launch within a few weeks, while bespoke designs, ecommerce and custom functionality need more design, development and testing time. The table shows typical UK timelines, assuming content and feedback arrive on schedule.

Our website development service page explains how we plan and run projects of each size.

Typical website build timelines by type of site
Type of website Typical timeline What takes the time
Template-based starter site 1–3 weeks Set-up, content entry, basic testing
Small business site 4–8 weeks Custom design, content, testing
Custom WordPress site 4–8 weeks Bespoke theme, editor set-up, training
Ecommerce site 6–12 weeks Products, payments, shipping, legal pages
Bespoke corporate site 2–4 months Stakeholders, larger sitemap, integrations
Web application 3–6+ months Specification, custom logic, security, testing

Indicative UK market timelines, not a Freehand HQ commitment. Your schedule depends on scope, content and approvals.

What are the phases of a website project?

Most website projects follow five phases: discovery and planning, design, development, testing, and launch. Each phase ends with something you review and approve, which keeps the project on track. Discovery and content preparation are the phases most often rushed, and they are usually the main reason later phases overrun.

Phases often overlap: development can start on agreed templates while later pages are still in design. For a typical small business site, discovery and design together take a few weeks, and development and testing take the rest.

  1. Discovery and planning: goals, audience, sitemap, features and content plan.
  2. Design: page designs for mobile and desktop, with review rounds.
  3. Development: building templates, features and integrations on a staging site.
  4. Testing: devices, browsers, accessibility, speed, forms and security.
  5. Launch: go-live, redirects, Search Console set-up and training.
Related service · 01 Website Development Custom websites, e-commerce platforms and web applications — built to perform and built to scale.

What causes website projects to be delayed?

The most common cause of delay is content: copy, images and product data arriving late. Other causes are slow feedback, too many decision-makers, scope changes after design sign-off, waiting for third-party accounts or access, and underestimating the work of moving content from an old site. Most delays are avoidable with planning.

  • Late content: start writing before design begins.
  • Slow approvals: agree one decision-maker and feedback deadlines.
  • Scope creep: log new ideas for phase two instead of adding them mid-build.
  • Access and accounts: gather domain, hosting, payment and analytics logins early.
  • Migration surprises: audit old content and URLs at the start.

How can you speed up a website build?

The fastest projects have a clear brief, content ready before design starts, one decision-maker and a fixed scope for launch. Using a proven platform such as WordPress rather than building everything from scratch also saves time. Launching a focused first version, then adding features later, is often quicker and less risky.

If you need to be live quickly for a campaign, a single landing page can often launch in 1–3 weeks while the full site is built. Our guide to WordPress vs a custom website explains how platform choice affects timelines.

Does a website redesign take less time than a new site?

Not always. A redesign can reuse content and structure, which saves planning time, but it adds work: auditing existing pages, mapping old URLs to new ones with 301 redirects and protecting search rankings. For most businesses a redesign takes a similar time to a new build of the same size.

Our website redesign checklist lists the steps that protect traffic during a redesign.

What should you prepare before the project starts?

Before kickoff, prepare a short brief, a list of pages, your logo and brand guidelines, examples of sites you like, draft copy for key pages, good photography, and access to your domain and any existing hosting. Having these ready can cut weeks off a typical timeline and makes quotes more accurate.

  • Business goals and the main action you want visitors to take.
  • A rough sitemap and any must-have features.
  • Brand assets: logo files, colours, fonts.
  • Draft copy and photos for the most important pages.
  • Logins for domain, hosting, analytics and Google Business Profile.
  • A realistic budget range. See website design costs in the UK.

What happens after a website launches?

Launch is the start, not the finish. In the first few weeks you should check Google Search Console for indexing errors, confirm redirects and forms work, monitor speed, and fix any issues visitors report. After that, a website needs regular software updates, backups and content reviews to stay secure and useful.

  • Submit the XML sitemap and check indexing in Google Search Console.
  • Test every form and confirm enquiries arrive.
  • Check old URLs redirect correctly if the site replaced an old one.
  • Review analytics after a few weeks to see which pages bring enquiries.
  • Agree who applies updates and backups. Our website maintenance plans cover this.

Sources and further reading

FAQ

Website timeline
questions, answered.

Can a website be built in a week?

A simple template-based site with ready content can sometimes launch in about a week. Anything with custom design, ecommerce or integrations needs longer if it is to be tested properly, accessible and fast.

How long does an ecommerce website take?

A typical Shopify or WooCommerce site takes around 6–12 weeks. Product data, photography, shipping rules and payment set-up often take longer than the design. Bespoke or high-volume ecommerce can take several months.

When should I start writing content?

As early as possible, ideally before design begins. Designers work better with real content, and late copy is the most common reason website launches slip. Start with your homepage and main service pages, then fill in the rest.

How long after launch will my site appear on Google?

Search engines can discover a new site within days once it is submitted through Google Search Console with an XML sitemap. Ranking well for competitive searches takes longer and depends on content quality, links and competition, so no one can guarantee positions.